Priority Setting Partnership Timeline

October - December 2016
  • Form steering group
  • Scope priority setting question
January - March 2017
  • Review literature and previous PSPs
  • Design and pilot survey
April - June 2017
  • Consult and finalise survey
  • Prepare for launch
July - September 2017
  • Run priority setting survey
  • Analyse responses to categoriese data
  • Produce long list of research questions
October 2017 - February 2018
  • Prioritisation process to rank the questions
March 2018 - April 2018
  • Run interim priority setting survey
  • Produce short list of research questions
  • Run final priority setting workshop
May 2018 onwards
  • Launch top 10 unanswered research questions on multiple conditions in later life
  • Publicise and disseminate the findings